Landlord Approvals for Office Fit Out

Almost every commercial lease says you need the landlord’s written approval before doing building work in your office. Getting that approval early, with the right documents, keeps a fitout on schedule. This guide explains what landlords usually ask for, how…

Black-framed glass offices with frosted bands and timber-look plank flooring at Tasha Care in Northcote
Since 1985 Melbourne office specialists3,500+ workplaces deliveredOne team from plan to handover

Almost every commercial lease says you need the landlord’s written approval before doing building work in your office. Getting that approval early, with the right documents, keeps a fitout on schedule. This guide explains what landlords usually ask for, how long it takes and how to avoid delays.

Why landlord approval is needed

The landlord owns the building and its services, and is responsible for the base building: the structure, air conditioning plant, fire services and common areas. Any work that touches those, or changes the tenancy, needs their consent under the lease. Many leases also set rules for contractors, working hours and how the space must be returned at the end of the lease.

What landlords usually ask for

  • Floor plans and drawings of the new layout
  • Reflected ceiling plans showing lights, air conditioning and sprinklers
  • A scope of works and finishes schedule
  • Electrical, mechanical and fire services details
  • The builder’s insurances and licences
  • Safe work method statements and a construction program
  • Details of any structural, plumbing or penetration work
  • A copy of the building permit, if one is needed

Landlord consultants and fees

Larger buildings often have the landlord’s own engineers review the services drawings, especially air conditioning and fire services. Some leases make the tenant pay for those reviews. Check your lease so the fee is in your budget.

How long landlord approval takes

It can be a few days for a simple scope in a small building, or several weeks for a large fitout with services changes. Complete drawings and a clear scope shorten the process. Lodge as soon as the layout is settled.

Building rules during the work

  • Hours for noisy work, often outside business hours
  • Booking lifts and the loading dock
  • Protecting common areas and lifts
  • Fire system isolations, which usually go through the building’s fire contractor
  • Inductions for trades working in the building

Think about the end of the lease

Whatever you build, the lease may require you to remove it when you leave. Ask the landlord now which parts of the fitout can stay. Our make good guide explains why this matters.

How we handle it

On our projects we prepare the drawings and documents, lodge them with the building manager, answer the consultants’ questions and line up the building permit. Our fitout permits guide covers the permit side.

Need landlord approval for a fitout? Tell us about your office or call 1300 903 935. We answer enquiries within the hour during business hours.

Ready to make your space work harder?

Speak with us about a Melbourne commercial office project.

Book a free site measure